[Nagios-devel] check_period, timeperiod exclusions,

Support forum for Nagios Core, Nagios Plugins, NCPA, NRPE, NSCA, NDOUtils and more. Engage with the community of users including those using the open source solutions.

[Nagios-devel] check_period, timeperiod exclusions,

Postby Guest » Fri Oct 12, 2012 4:27 pm

Hi - we've just encountered some unexpected behaviour where the next
check time for a service gets set to 00:00 tomorrow when we enter a
a timeperiod exclusion. It seems like it might be a bug in check_period
timeperiod handling, but I have no idea where to start looking in the code.

I have a service defined with "check_period not_fridayaft", and the timeperiods
defined like this:

define timeperiod {
timeperiod_name not_fridayaft
alias not friday aft
use 24x7
exclude fridayaft
}
define timeperiod {
timeperiod_name fridayaft
alias friday aft
friday 12:45-12:55
}

At 12:45 Friday, the service state information page starts showing:

Next Scheduled Check: 10-13-2012 00:00:00

and the service is not checked until Saturday rolls around.

But, if I redefine the timeperiod to be explicit, and not use exclude, like this:

define timeperiod {
timeperiod_name not_fridayaft
alias not friday aft
sunday 00:00-24:00
monday 00:00-24:00
tuesday 00:00-24:00
wednesday 00:00-24:00
thursday 00:00-24:00
friday 00:00-12:45,12:55-24:00
saturday 00:00-24:00
}

restart Nagios, and the service's next check time shows up correctly:

Next Scheduled Check: 10-12-2012 12:55:00

This is 3.4.1, which I built based on nagios-3.4.1-2.el6.src.rpm using a
nagios.spec build file with the last modification:
* Thu Jun 28 2012 Petr Pisar - 3.4.1-2
The nagios.spec adds a few patches, but I don't see anything that makes me
think it would trigger this.

Has anyone else seem anything like this? I've got a workaround (by avoiding
the exclude), but it makes me wonder if there's a bug in the timeperiod
exclusion handling code.

Thanks - cheers!

John
jsellens@syonex.com






This post was automatically imported from historical nagios-devel mailing list archives
Original poster: jsellens@syonex.com
Guest
 