Availability reports not respecting time period
Posted: Fri Feb 21, 2014 5:35 am
When generating a report from 2013-10-01 to 2013-12-31 for a servicegroup that I created for these reports, and selecting a custom time period for Monday - Friday 07:00 - 18:00 (workhours), Nagios says it's calculating 92 days and 1 hour.
I'm trying to understand how the reports work because yes there are 92 days between 2013-10-01 and 2013-12-31 but there are not 92 working days with that timeperiod (Monday - Friday, 07:00 - 18:00).
So which is correct? Do the availability reports ignore the timeperiod?
I would like to extract a report that honors the timeperiod I select. That is my goal.
I'm trying to understand how the reports work because yes there are 92 days between 2013-10-01 and 2013-12-31 but there are not 92 working days with that timeperiod (Monday - Friday, 07:00 - 18:00).
So which is correct? Do the availability reports ignore the timeperiod?
I would like to extract a report that honors the timeperiod I select. That is my goal.